Skip to main content
Back to Resources
Implementation Guide

SMED Implementation Guide for CNC

Build a repeatable 90-day setup-time reduction program

What is SMED?

SMED (Single-Minute Exchange of Dies) is a lean manufacturing methodology developed by Shigeo Shingo at Toyota to reduce setup times to under 10 minutes (single-digit minutes, hence "single-minute").

For CNC machining, SMED focuses on reducing changeover time between jobs—from finishing the last good part of Job A to starting the first good part of Job B.

Why SMED Matters (illustrative model):

Before SMED:

  • • Setup: 45 minutes average
  • • 8-hour shift = 10 setups max
  • • 420 minutes lost/day (87.5%)

After SMED (50% reduction):

  • • Setup: 22 minutes average
  • • 8-hour shift = 21 setups possible
  • 210 minutes saved/day

The Three Core Principles

  1. Separate internal and external activities - Do as much as possible while machine is running
  2. Convert internal to external - Move activities outside the critical path
  3. Streamline remaining activities - Eliminate waste in unavoidable downtime

Setup Time: Before vs. After SMED

Before SMED: 45 Minutes

Remove parts
5 min
Get tools/fixtures
9 min
Change vise
11 min
Load tools
6 min
Measure tools
8 min
Set work zero
6 min
Total Downtime
45 min
75% waste time

After SMED: 22 Minutes (-51%)

Remove parts
3 min
Get tools
External (pre-staged)
Change vise
4 min
Load tools
4 min
Measure tools
External (presetter)
Set work zero
2 min
First part check
9 min
Total Downtime
22 min
+51% capacity!
Annual Capacity Gain (4 setups/day, 250 days/year)
23 min × 1,000 setups = 383 hours = 9.6 weeks of production

Step 1: Classify Activities (Internal vs. External)

Internal Activities

Must be done while machine is stopped

  • ✓ Remove finished part from machine
  • ✓ Change workholding (vise, chuck, fixture)
  • ✓ Install new part in fixture
  • ✓ Touch off tools (tool length measurement)
  • ✓ Set work zero (part origin)
  • ✓ Run first article inspection

External Activities

Can be done while machine is running

  • ✓ Gather tools and fixtures for next job
  • ✓ Pre-set tool lengths on tool presetter
  • ✓ Review and verify CNC program
  • ✓ Prepare raw material (deburr, clean)
  • ✓ Stage tooling at machine door
  • ✓ Print job traveler and setup sheets

SMED Goal:

Move as many activities as possible from the Internal (red) column to the External (green) column. Every minute moved = one more minute of production capacity.

90-Day SMED Implementation Plan

Days 1-30

Phase 1: Measure & Analyze

Week 1-2: Baseline Measurement

  • Film 5-10 complete setups with smartphone (get operator consent)
  • • Time each activity with stopwatch: "Remove part: 3:45, Get vise: 2:30..."
  • • Calculate average setup time and breakdown by activity
  • • Identify top 3 time-consuming activities (Pareto analysis)

Week 3-4: Team Kickoff

  • • Form SMED team: 1 supervisor, 2-3 operators, 1 programmer
  • • Watch setup videos together, classify internal/external
  • • Brainstorm improvement ideas (no idea too small!)
  • • Set target: e.g., "Reduce 45-min avg to 22-min in 90 days"
Days 31-60

Phase 2: Quick Wins Implementation

ImprovementActionTime-Saving Estimate
Pre-stage next jobKitting: cart with tools, fixtures, material ready before current job endsValidate onsite
Tool presettingMeasure tool lengths offline with presetter (not on machine)Validate onsite
Quick-change visesInstall sub-plates with repeatable locating pinsValidate onsite
Standard work zeroUse same G54 offset for common fixture, eliminate re-touchingValidate onsite
Shadow boardsTool storage with labeled outlines (wrenches, allen keys, etc.)Validate onsite

Expected total savings from quick wins: validate cumulative reduction with timed trials on your own setup families.

Days 61-90

Phase 3: Standardize & Sustain

Create Standard Work Documents

  • • Write setup procedure for each machine (with photos)
  • • Include tool list, fixture setup, work offset procedure
  • • Laminate and post at each machine

Train All Operators

  • • 2-hour training session on new SMED procedures
  • • Hands-on practice with presetter, quick-change fixtures
  • • Certify each operator (skills checklist)

Measure and Improve

  • • Track setup time weekly (plot on chart)
  • • Monthly SMED review meeting: celebrate wins, address issues
  • • Continuous improvement: set a quarterly reduction target from actual trend data

Top 10 SMED Techniques for CNC

1

Tool Presetting Station

Offline tool presetter measures tool lengths before job starts. Eliminates 6-10 min of on-machine touching.

Investment: Vendor-quote based for your presetter scope

Payback: Compute from measured setup-time recovery and loaded machine rate

2

Quick-Change Fixture System

Sub-plates with dowel pins allow fixtures to be mounted in exact same position every time. Zero re-indicating.

Example: System 3R, Erowa, Schunk VERO-S

Time saved: Validate per setup family with stopwatch data

3

Dedicated Fixture Library

Pre-build fixtures for common part families. Store on labeled shelves next to machine.

Strategy: Build 3-5 common fixtures (e.g., "4-inch vise," "angle plate 30°")

Result: Grab-and-go fixture selection (no custom build per job)

4

Work Offset Standardization

Use consistent work zero locations (e.g., G54 = vise jaw corner) across all jobs with same fixture.

Benefit: No touching work zero each setup—programmed offset is always correct

Time saved: Validate with pilot runs on repeat part families

5

Job Kitting / Setup Cart

Pre-stage all tools, fixtures, material, and paperwork for next job on a cart 30 minutes before current job ends.

Implementation: Simple rolling cart with checklist

Time saved: Measure in your environment after kitting standardization

6

Standardized Tooling

Keep common tools (e.g., 1/2" endmill, #7 drill) assembled in holders at all times. Don't disassemble after each job.

Tip: Buy duplicate holders for high-use tools after confirming handling bottlenecks in setup observation.

7

Visual Setup Sheets

Photo-based instructions showing exact fixture orientation, part location, tool list with pictures.

Format: Laminated A4 sheet: photo of setup + tool list + work offset values

Result: Less confusion = faster, error-free setups

8

Eliminate Adjustments

Replace adjustable fixtures with fixed, repeatable designs. No tramming, no dialing in.

Example: Replace adjustable angle plate with fixed 45° wedge fixture

Philosophy: "Set it once, use it forever"

9

Tool Crash Prevention

Use simulation software (Vericut, NCSimul) to verify programs before first part. Eliminates trial-and-error.

Benefit: Reduces trial-and-error during prove-out and improves safety margin for first runs.

Bonus: Lowers crash risk when simulation discipline is consistently applied.

10

Two-Operator Setup (Complex Jobs)

For large/heavy setups, assign 2 people. Parallel work = faster completion.

Example: Operator A loads material, Operator B stages tools simultaneously

When to use: Setups >30 min with 2+ people available

SMED Financial Impact Calculator

This section is an illustrative financial model. Replace all inputs with your measured setup times, rates, and staffing costs before making decisions.

Example Shop Scenario

Setups per day10
Avg setup time (before SMED)45 min
Avg setup time (after SMED)22 min
Time saved per day230 min (3.8 hrs)
Machine rateUse your loaded rate
Working days/yearUse your production calendar

Financial Benefits

Daily capacity gainFrom your measured delta
Daily value recoveredCapacity gain × loaded rate
Annual valueDaily value × working days
SMED implementation costSum of your actual implementation items
(e.g., presetter, fixtures, training, standard-work development)
Payback periodImplementation cost ÷ daily recovered value

Common SMED Implementation Pitfalls

Skipping baseline measurement

Without timing current setups, you can't prove improvement or prioritize actions. Always measure first.

Operator resistance ("We've always done it this way")

Involve operators early in brainstorming. Their buy-in is critical—they know the pain points best.

Over-investing in automation too early

Start with low-cost fixes (shadow boards, kitting) before buying expensive quick-change systems.

No follow-up tracking

SMED gains erode without continuous monitoring. Track setup times weekly on a visible chart.

Trying to fix all machines at once

Start with one "pilot" machine. Perfect the process, then roll out to others.

SMED Success Metrics

Track these KPIs to measure SMED effectiveness:

Avg Setup Time
Trend Down
Primary metric
OEE (Availability)
Trend Up
More uptime
Setups per Day
Track Weekly
More flexibility
Setup Errors
Trend Down
Less scrap

Related Resources

Use our calculators to understand how SMED impacts overall equipment effectiveness: